Home
Subscribe | Advertise | Place an Ad | Archives | E-edition | RSS Feeds | Contact Us
Site search
sponsored by
 
Welcome, Guest 
avatar

Please enter the following information:

Email:
Password:
  Remember Me
 
  Forgot Password?
  Become a Member
  Close Window
Glenwood Springs, Colorado | Post Independent
Jobs
Glenwood Springs, Colorado | Post Independent
Autos
Glenwood Springs, Colorado | Post Independent
Real Estate
Glenwood Springs, Colorado | Post Independent
Classifieds
Glenwood Springs, Colorado | Post Independent
Search local dealer inventory and private seller listings
Search for homes by MLS, classified listings, rentals, and much more!
Glenwood Springs, Colorado | Post Independent
Home
<< back
Friday, May 2, 2008
Environmental groups can't stop pipeline construction
Judge denies motion to block a gas line crossing roadless areas
Print Comment
ASPEN, Colorado — Pitkin County and a coalition of environmental groups failed to get a temporary injunction to block a natural gas exploration company from constructing a pipeline through roadless areas of western Colorado.

A federal judge on Wednesday denied a motion for the injunction.

“The plaintiffs have not demonstrated a substantial likelihood that they will prevail eventually on the merits of their roadless rule or their National Environmental Protection Act claim,” ruled U.S. District Judge Robert Blackburn in Denver.

The decision clears the way for work on the pipeline to start this month. Pitkin County officials fear the construction of that pipeline could trigger development of gas wells in western Pitkin County, outside of Carbondale. No new production wells have been drilled in Pitkin County since the gas boom started earlier this decade. However,
thousands of acres of public lands have been leased to gas companies.

Wilderness Workshop, the oldest grassroots environmental group in the Roaring Fork
Valley, is among the plaintiffs teamed with Pitkin County.

“It’s disappointing, of course,” Wilderness Workshop Executive Director Sloan
Shoemaker said of the ruling. “We’re considering what our options are,”

The environmental coalition and Pitkin County filed a lawsuit in March against the
U.S. Forest Service and Bureau of Land Management over their approval of the Bull
Mountain Pipeline in Garfield County. The plaintiffs claimed the agencies violated
federal law by approving a pipeline, which will require roads for construction, in a
roadless area. A Texas firm called SGI Interests wants to build the pipeline through
three roadless areas of national forest.

The federal agencies claimed that the pipeline would require temporary construction
areas rather than roads, so there was no violation of the roadless rule. Blackburn
ruled in their favor on that point.

The environmental groups and Pitkin County also argued that the pipeline would
clear the way for more gas wells to be developed on public lands. They claimed the
agencies didn’t do any analysis of the environmental consequences of those new
wells.

But Blackburn ruled that the pipeline was viable to serve existing wells. It will not
automatically trigger drilling of new wells, he determined.

Pitkin County Assistant Attorney Chris Seldin said county officials feel it is much more
likely gas wells will be developed if the pipeline is built. SGI holds 13 gas leases on
17,170 acres in Pitkin County, Shoemaker said. All those leases are within the White
River National Forest.

The pipeline itself doesn’t enter Pitkin County, but it would connect to existing
pipelines. The Bull Mountain Pipeline would be 25.5 miles long and connect to a
larger pipeline running near Interstate 70.

The judge concluded in his ruling that the plaintiffs “will suffer some irreparable
injury” from construction of the 8 miles of the pipeline through roadless areas. “The
100-foot wide right-of-way will be stripped of trees and other vegetation and graded
to accommodate construction vehicles,” his ruling said. “Nine acres of spruce/fir old
growth and 29 acres of aspen old growth will be removed, and generally trees will
not be permitted to grow in the pipeline right-of-way.”

That work could result in greater risk of erosion and turn land that is suitable as lynx
habitat into unsuitable, the judge acknowledged. However, he said there was also a
public interest in the construction of the pipeline and that SGI’s economic interests
would be harmed if the work didn’t progress.

“I conclude that the balance of harms in this case is roughly a wash,” the judge wrote.

His denial of the temporary injunction doesn’t eliminate the lawsuit. However, the
pipeline could be finished by the time the litigation is resolved. Seldin said the
attorneys for the plaintiffs hadn’t decided as of Thursday morning if they will appeal
the decision.


Print del.icio.us digg reddit
Other Top Items
Related Articles
Most Recommended Articles
Comments
About Us | Staff | Site Map | Privacy Policy | Terms of Use | Swift Communications