Glenwood hoping for ‘minimal’ impacts | PostIndependent.com
YOUR AD HERE »

Glenwood hoping for ‘minimal’ impacts

John Gardner
Post Independent Staff
Glenwood Springs, CO Colorado
Kelley Cox Post IndependentThe Grand Avenue Bridge in Glenwood Springs will have some work done as part of the Colorado Department of Transportation plan that includes the Interstate 70 exit 116 area.
ALL |

GLENWOOD SPRINGS, Colorado – Traffic impacts are expected to be “minimal” during the duration of the Interstate 70, Exit 116 Glenwood Springs interchange project.

The project, which began Monday, is scheduled to last until Nov. 24, with a majority of the work being performed during the night between the hours of 9 p.m. and 6 a.m., according to project manager from Scott Contracting Matt Varholdt.

Varholdt also said, that construction could be wrapped up by as early as Oct. 21, depending on how smoothly the project goes.



“That is the date we want to be completed by,” Varholdt said.

While the project is considered relatively small in scale, according to Colorado Department of Transportation Project Engineer Joe Elsen, the most challenging aspect when dealing with intersections like the main Glenwood Springs exit is the sheer volume of traffic that passes through each day.



“Traffic is definitely the biggest challenge with this kind of project,” Elsen said.

According to CDOT, the intersection had an average annual daily use of 25,800 vehicles in 2008. That number may seem a little low, according to CDOT spokeswoman Nancy Shanks, because it is an average for the entire year. Shanks said that during the peak of the summer tourist season the intersection more likely sees upwards of 45,000 vehicles in a single day.

Crews began Monday, setting up construction barriers in preparation to begin preliminary construction work early next week. Varholdt said that crews will not be working on Labor Day weekend, and no lane closures will occur during the holiday weekend. Crews will begin the bulk of the project after the Labor Day weekend.

The project received $2.5 million in stimulus funds through the American Recovery and Reinvestment Act of 2009, and an additional $162,000 from the Federal Congestion Relief Funds. The design of the project is to ease heavy traffic flows during morning and evening commutes. The work will include additional lanes on the I-70 entrance and exit ramps to the west side of Highway 82, re-paving work through Sixth Street and over the Grand Avenue Bridge, a second turn lane and new traffic lights will be added at the Sixth and Pine Street intersection. Conduits and fiber optic cables will be installed to align signals at the multiple intersections to better allow for mobility during rush hours.

Varholdt said that with most work occurring at night, motorists who can not avoid the intersection during rush hours should not expect major delays. And while some lane closures could

during the day, Varholdt ensured that work would not be occurring during rush hour times.

City Engineer Mike McDill said that bus schedules during the project would not be affected either. McDill said that he’s already spoken with Varholdt and that with the work being performed at night, would allow for busses to continue their regular schedule for the duration of the project.

McDill also expects an increase of traffic on Midland Avenue with motorists attempting to bypass the 116 Interchange, however with construction ongoing at the south end of Midland Avenue on the roundabout at the 27th Street intersection, that could make for more congestion on that street.

But, according to Assistant City Engineer Steve Vanderleest, the roundabout should be accommodating traffic the week of Sept. 7, after the Labor Day weekend. However, Midland Avenue will be closed to through traffic at 27th Street, starting Monday, Aug. 24 through Aug. 30, as crews will be tying in the 27th Street roundabout at Midland Avenue. South Midland Avenue traffic will be able to utilize the current bypass during this time.

The first week of September crews will finish tying in the other two legs of 27th Street into the roundabout, allowing traffic to flow.

As for some concerns brought up by the Glenwood Springs City Council in July, regarding pedestrian crossing improvements at the Sixth Street and Laurel Street intersection. City Council requested that the work include three concrete pedestrian crossings at the intersection, however, the request was not included in plans.

According to Elsen, CDOT and Scott Contracting has come up with some alternatives to the request that will be presented to City Council at its Sept. 3 meeting.

City Councilwoman Shelley Kaup said that council has scheduled a work session with CDOT on Sept. 3 to discuss the issue. As of Wednesday, Kaup said that she has not heard any specifics as to what the alternatives were.

Throwing another wrinkle into the project is the 25th Annual Tri-Glenwood Triathlon, which is scheduled for Sunday, Sept. 13. According to Tom Newland, project spokesman for Scott Contracting, accommodations will be made for the expected 300 cyclists who will follow a route that will utilize both the westbound I-70 116 on ramp, and the eastbound I-70 116 exit ramp.

“We have made contact with the organizer and are going to take care of everything,” Newland said.

jgardner@postindependent.com


Support Local Journalism

Support Local Journalism

Readers around Glenwood Springs and Garfield County make the Post Independent’s work possible. Your financial contribution supports our efforts to deliver quality, locally relevant journalism.

Now more than ever, your support is critical to help us keep our community informed about the evolving coronavirus pandemic and the impact it is having locally. Every contribution, however large or small, will make a difference.

Each donation will be used exclusively for the development and creation of increased news coverage.

 

Start a dialogue, stay on topic and be civil.
If you don't follow the rules, your comment may be deleted.

User Legend: iconModerator iconTrusted User